Upper Serpentine Drainage Pump Station

Owner
City of Surrey, Vince Lalonde, 604-591-4314

Engineer
Associated Engineering, Vladimir Markovic, 604-293-1411

Completed Value
$1.5 million

Construction Period
June 2000 to April 2001


Scope of Work
The project involved construction of a stormwater pump station on the bank of the Serpentine River, along with upgrading of the incoming drainage channel. The outlet area was temporarily sheet piled to isolate the excavation from the river, and the concrete structure was supported on precast concrete piles. Two large screw pumps were installed, along with an electrical control building and an overhead power line.